Insights from 26 completed projects
26
Completed Projects
13,320
Subtask Entries Tracked
10,393
Deviation Logs
121
Vendors

Task Delay Ratios — Planned vs Actual Duration

Based on completed projects, here's how much longer each task type actually takes compared to what was planned.

Task Category Task Name Instances Avg Planned Avg Actual Delay Ratio Avg Slip

Why Tasks Get Delayed

Top deviation reasons across all projects

Material issues account for 37% of all delays, client-related issues for 22%, and labor for 13%.

Project Delivery Track Record

Completed projects with planned vs actual duration

Project Client / City Planned Actual Duration Ratio

Vendor Reliability Rankings

On-time performance and average slip by vendor

Vendor Projects Subtasks On-Time % Avg Slip
Client On-Time Performance
Percentage of subtasks completed on time by client brand
Key Takeaways
Actionable insights from historical project data
📅
Projects typically take 1.22x the planned duration. Only 3 out of 16 tracked projects finished on or before time.
📦
Material delivery is the #1 delay reason (27% of all deviations), affecting 41 out of 46 projects with deviation data.
MEP tasks (Fire Alarm, CCTV, HVAC, Electrical) consistently have the worst delay ratios — 3–13x planned. Plan buffer accordingly.
🎨
Painting tasks (Plastic Emulsion, Premium Emulsion) reliably take 2.5x the planned duration across 157+ instances — this is a systemic planning gap.
J

Ask Jarvis

Query MyGenie data with natural language

Stats about Chandu vendor Which tasks delay the most? Compare Cult Hybrid vs Mokobara projects Top delay reasons for painting How many snags in HRBR Layout? Vendor reliability for Pune projects
Hi! I can query the MyGenie database for you. Ask me about vendors, projects, task delays, deviation reasons, snags, or anything else from the data.